PROJECT OVERVIEW
Cook County, in partnership with the Illinois Department of Transportation (IDOT) and the Village of Skokie, will complete a major roadway improvement on Old Orchard Road from Woods Drive to Skokie Boulevard. When completed, the project will alleviate congestion, increase safety and expand access to pedestrians and people biking through the addition of the following improvements:
- New turn lanes at the I-94 eastbound ramps and Old Orchard Road intersection.
- Roadway and bridge widening (from Woods Drive to Skokie Boulevard including the IDOT bridge over I-94).
- Installation of storm sewers, traffic signals and lighting.
- A new multi-use path on the south side of Old Orchard Road within the project limits, providing direct access to the North Branch Cook County Forest Preserve Trail.
- Intersection improvements at Old Orchard Road and Woods Drive.
- Intersection improvements at the I-94 westbound exit ramp, eastbound exit ramp, westbound entrance ramp, Lawler Avenue, Lavergne Avenue, Bronx Avenue and Lamon Avenue intersections with Old Orchard Road.
LATEST INFORMATION
|
NOVEMBER 12, 2026
Part of the project’s work includes the complete reconstruction of the intersection of Lavergne Avenue at Old Orchard Road. Crews will close the northern leg of the Lavergne Avenue intersection on Thursday, November 12. The intersection will re-open on new pavement on Tuesday, November 17. This closure allows the contractor to complete all remaining concrete work at one time, so crews can install the new asphalt overlays in one operation. All traffic from Lavergne Avenue and Culver Street will detour through Bronx, Lamon or Lacrosse Avenues. |
OCTOBER 27, 2026
The project team is excited to reach the key milestone of opening the southern bridge of Old Orchard Road over I-94 this weekend to traffic. This will allow the shift of traffic from the existing north bridge to the new south bridge, maintaining one lane of traffic in each direction while project construction continues. The shift is anticipated to be completed late Friday, October 30 evening or early Saturday, October 31 morning.
With the completion of the south bridge, the new shared-use path will open the week of November 9 on the south side of Old Orchard Road from Woods Drive to Skokie Boulevard, providing a connection as well to the existing trails in the Forest Preserve to the west.
The contractor will continue working on the project through the winter with activities focused on demolition of the north bridge first - which is anticipated to be completed by the end of 2026. Replacement of the bridge pier in the median of I-94 as well as modifications to the east and west bridge abutments for the north bridge are also anticipated this winter.
Once the demolition of the remaining portion of the north bridge is complete in late December, a new temporary traffic signal will be installed at Old Orchard Road and westbound I-94, allowing traffic from westbound Old Orchard Road to travel onto westbound I-94 as well as exiting traffic from westbound I-94 to westbound Old Orchard Road for passenger cars only.
The project team is excited to reach the key milestone of opening the southern bridge of Old Orchard Road over I-94 this weekend to traffic. This will allow the shift of traffic from the existing north bridge to the new south bridge, maintaining one lane of traffic in each direction while project construction continues. The shift is anticipated to be completed late Friday, October 30 evening or early Saturday, October 31 morning.
With the completion of the south bridge, the new shared-use path will open the week of November 9 on the south side of Old Orchard Road from Woods Drive to Skokie Boulevard, providing a connection as well to the existing trails in the Forest Preserve to the west.
The contractor will continue working on the project through the winter with activities focused on demolition of the north bridge first - which is anticipated to be completed by the end of 2026. Replacement of the bridge pier in the median of I-94 as well as modifications to the east and west bridge abutments for the north bridge are also anticipated this winter.
Once the demolition of the remaining portion of the north bridge is complete in late December, a new temporary traffic signal will be installed at Old Orchard Road and westbound I-94, allowing traffic from westbound Old Orchard Road to travel onto westbound I-94 as well as exiting traffic from westbound I-94 to westbound Old Orchard Road for passenger cars only.
SEPTEMBER 30, 2026
The project team is excited to share videos of the recent work on the south bridge over I-94 to the Photo Gallery. These videos show the installation of the new beams that support the bridge deck which were delivered to the site on trucks and fitted with the bearings and plates needed to affix them to the bridge abutments, piers and each other. Each beam was lifted into place over the closed lanes of the expressway while ironworkers fit each beam in place and lock them together with bolts and impact wrenches.
There are also videos of the concrete bridge deck pour. Concrete was transferred to the bridge deck through a conveyor pump. The videos show the pump discharging concrete onto the reinforcing bars as well as the work platform moving slowly across the deck leveling the concrete; the laborers and concrete finishers are following the work platform to smooth and seal the concrete surface.
The project team is excited to share videos of the recent work on the south bridge over I-94 to the Photo Gallery. These videos show the installation of the new beams that support the bridge deck which were delivered to the site on trucks and fitted with the bearings and plates needed to affix them to the bridge abutments, piers and each other. Each beam was lifted into place over the closed lanes of the expressway while ironworkers fit each beam in place and lock them together with bolts and impact wrenches.
There are also videos of the concrete bridge deck pour. Concrete was transferred to the bridge deck through a conveyor pump. The videos show the pump discharging concrete onto the reinforcing bars as well as the work platform moving slowly across the deck leveling the concrete; the laborers and concrete finishers are following the work platform to smooth and seal the concrete surface.
SEPTEMBER 23, 2026
Old Orchard Road work continues on target to switch traffic to the new southern half of the bridge at the end of October. Roadway users should also expect to see the ramp for westbound/outbound I-94 open to westbound Old Orchard Road traffic in November.
Recent work on the project includes the completion of the new south bridge deck. The new concrete base for the roadway pavement from Lamon Avenue to Lawler Avenue was also completed. Next steps on the bridge include the installation of a fence and a concrete parapet wall separating the pedestrian path from the traffic lanes. Upcoming work also includes the completion of concrete roadway pavement along the north side of the roadway and the installation of electrical foundations for traffic signals and roadway lighting.
Old Orchard Road work continues on target to switch traffic to the new southern half of the bridge at the end of October. Roadway users should also expect to see the ramp for westbound/outbound I-94 open to westbound Old Orchard Road traffic in November.
Recent work on the project includes the completion of the new south bridge deck. The new concrete base for the roadway pavement from Lamon Avenue to Lawler Avenue was also completed. Next steps on the bridge include the installation of a fence and a concrete parapet wall separating the pedestrian path from the traffic lanes. Upcoming work also includes the completion of concrete roadway pavement along the north side of the roadway and the installation of electrical foundations for traffic signals and roadway lighting.
STAY CONNECTED
|